* Board reserves the right to require multiple taps for 1 1/2-inch and 2-inch.
If a tapping saddle is required, the cost and sales tax of tapping saddle shall be added to the above fees. If this cost difference is critical to bid proposals, it is recommended that the size of water main to be tapped be checked before a project is estimated.
II. 1 1/2-inch and 2-inch single corp taps with saddles *
Tap
$Mat
$Labor
$Equip
$Total
4" x 1 1/2"
160
156
79
395
6" x 1 1/2"
163
156
79
398
8" x 1 1/2"
217
156
79
452
12"x 1 1/2"
279
156
79
514
16"x 1 1/2"
265
156
79
500
4" x 2"
205
156
80
441
6" x 2"
207
156
80
443
8" x 2"
261
156
80
497
12" x 2"
323
156
80
559
16" x 2"
310
156
80
546
(The above prices do not include sales tax)
* Board reserves the right to require multiple taps for 1 1/2-inch and 2-inch.
Any tap price shown above must be obtained through Board Service Department
III. 4-inch and larger: Asbestos-Cement (Transite)
Tap
$Mat
$Labor
$Equip
$Total
6" x 4"
653
302
170
1,125
6" x 6"
948
302
170
1,402
8" x 4"
672
302
170
1,144
8" x 6"
788
302
170
1,260
8" x 8"
1,383
302
170
1,855
12" x 4"
696
302
170
1,168
12" x 6"
811
302
170
1,283
12" x 8"
1,163
302
170
1,635
12" x 12"
2,274
302
170
2,746
16" x 4"
716
302
170
1,188
16" x 6"
844
302
170
1,316
16" x 8"
1,192
302
170
1,664
16" x 12"
2,005
302
170
2,477
(The above prices do not include sales tax. Note: Mat = Materials, Equip = Equipment)
IV. 4-inch and larger: Cast Iron or PVC
Tap
$Mat
$Labor
$Equip
$Total
6" x 4"
653
302
170
1,125
6" x 6"
785
302
170
1,257
8" x 4"
672
302
170
1,144
8" x 6"
927
302
170
1,399
8" x 8"
1,130
302
170
1,602
10" x 4"
674
302
170
1,146
10" x 6"
796
302
170
1,268
10" x 8"
1,142
302
170
1,614
12" x 4"
693
302
170
1,165
12" x 6"
903
302
170
1,375
12" x 8"
1,221
302
170
1,693
12" x 12"
1,941
302
170
2,413
16" x 4"
716
302
170
1,188
16" x 6"
844
302
170
1,316
16" x 8"
1,192
302
170
1,664
16" x 12"
2,005
302
170
2,477
(The above prices do not include sales tax.)
Any tap price not shown above must be obtained through Board Service Department.
V. Tapped couplings and tees: When provided by a customer, a charge of $100 shall apply.
VI. Notes:
A. All excavations, concrete thrust blocks, backfill, resurfacing, and permits are the responsibility of the contractor/owner.
B. See Board Rules and Regulations, Section 6, for complete explanation of taps, tap couplings, and tees.
C. Any questions regarding which cost pertains to a particular property or situation should be referred to the Board Service Department, 543-2217.
D. When abandoning old water services and corporations at the main, the Board Service Department must be notified. The Service Department will dispatch a water service representative to witness shutoff at the water main while excavation is still open. See Sections 6.06 and 7.03.